Panama’s Ministry of Commerce and Industries is expected to formalize a resolution by Tuesday, April 7, 2026, authorizing First Quantum Minerals (TSX: FM) to begin the removal and processing of a massive ore stockpile at the shuttered Cobre Panamá mine. The move, confirmed by Minister Julio Moltó, marks a significant shift in the government’s management of the idled asset, which has remained in a state of “preservation and safe maintenance” since late 2023.
The stockpile, which contains approximately 38 million tonnes of ore, is estimated to yield roughly 70,000 tonnes of copper. While the authorization allows for the processing of already extracted material, both government officials and company executives have emphasized that this does not constitute a full reopening of the mine. Instead, the initiative is being framed as a necessary measure to mitigate environmental risks and generate the capital required to maintain the site’s integrity.
The Resolution: A Strategic Pivot for Site Preservation
The anticipated resolution follows months of technical review and political deliberation. The Cobre Panamá mine, once one of the world’s largest new copper projects, was ordered to halt operations following a Supreme Court ruling in November 2023 that declared its contract unconstitutional. Since then, the facility has faced mounting costs associated with care and maintenance, estimated at $15 million to $20 million per month.
Minister Moltó noted that the decision to allow the processing of the 70,000-tonne stockpile serves a dual purpose. First, it addresses the physical stability of the ore. Stockpiled copper ore is susceptible to oxidation and the generation of acid rock drainage if left exposed to Panama’s tropical climate for extended periods. Second, the revenue generated from the sale of the resulting copper concentrate will be used to offset the ongoing costs of keeping the mine in a non-operational but safe state.
For First Quantum Minerals, the permit provides a much-needed operational window. Chief Executive Tristan Pascall clarified during a recent briefing that the processing phase would likely begin approximately three months after the final regulatory green light is granted. The company anticipates that the processing of the full 38 million tonnes will take approximately one year to complete.
Operational Logistics and Economic Impact
The logistics of processing 38 million tonnes of ore are substantial. The operation will require the reactivation of the mine’s primary crushing and milling circuits, though the actual extraction of new ore from the pits remains prohibited. This “processing-only” phase is expected to recall approximately 700 workers to the site, providing a small but notable boost to local employment in the Donoso district.
From a market perspective, the release of 70,000 tonnes of copper concentrate comes at a time of tightening global supply. Analysts have been monitoring the copper sector closely, especially following production cuts in other major regions. For instance, recent reports indicate that Ivanhoe has slashed production guidance for Kamoa-Kakula, adding pressure to a market already struggling to meet the demands of the global energy transition.

The financial proceeds from the Cobre Panamá stockpile will be subject to the existing royalty structure, ensuring that the Panamanian state receives a direct economic benefit from the mineral removal. Since the care and maintenance program began in 2024, Panama has already monetized over 122,000 tonnes of previously stored copper concentrate, generating nearly $30 million in royalties for public works.
Managing Environmental and Operational Risks
One of the primary drivers behind the government’s authorization is environmental stewardship. The 38 million tonnes of ore currently sitting on the surface represent a significant geochemical liability. If left unmanaged, the sulfur-bearing minerals in the ore can react with rainwater and air, creating acidic runoff that could impact local water systems.
By processing the ore, First Quantum can neutralize the material and move it into the mine’s Tailings Management Facility (TMF), which is designed for long-term, stable storage. This “controlled feed” to the TMF is considered a best-practice approach to closing out a stockpile that was never intended for permanent surface storage.

“This is about responsible site management,” a Ministry technician stated during a recent site visit. “Whether the mine eventually reopens or moves toward permanent closure, the current stockpile must be dealt with to prevent long-term degradation of the surrounding ecosystem.”
The Road to June: A Long-Term Decision Looming
While the processing of the stockpile is a short-term tactical move, the long-term fate of Cobre Panamá remains the subject of intense debate. The Panamanian government has set a target of June 2026 to reach a final decision on the mine’s future.
The upcoming months will likely involve a comprehensive environmental audit and a series of public consultations. The government is caught between the economic necessity of the mine: which previously contributed nearly 5% to Panama’s GDP: and the strong environmentalist sentiment that led to the 2023 protests.
First Quantum has updated its medium-term copper production guidance to reflect various scenarios, including the gradual return of Cobre Panamá to the global supply chain, though they remain cautious about making definitive claims before the June deadline.
| Year | Copper Production Guidance (Tonnes) |
|---|---|
| 2026 | 375,000 – 435,000 |
| 2027 | 410,000 – 470,000 |
| 2028 | 430,000 – 490,000 |
Source: First Quantum Minerals Quarterly Outlook, April 2026.
Broader Context in the Copper Mining Industry
The developments in Panama are occurring within a broader context of volatility in the metals and minerals sector. As demand for critical minerals remains high, the industry is seeing a mix of regulatory crackdowns and strategic breakthroughs. While Panama navigates its domestic copper crisis, other commodities are experiencing similar shifts. For example, the nickel market recently saw a 20% rally driven by production cuts in Indonesia, underscoring how quickly supply-side disruptions can alter the global outlook.
For investors following the sector, the Panama situation is a key component of the Skillings Stock Slam, as the eventual status of Cobre Panamá will significantly impact First Quantum’s valuation and the overall availability of copper on the world market.

Technical Hurdles and Site Stability
Restarting the mills after more than two years of relative inactivity presents technical challenges. First Quantum’s engineering teams have been conducting routine maintenance on the ball mills and flotation circuits to ensure that the “processing-only” phase can commence without mechanical failure.
The use of advanced flotation technology will be critical during this year-long processing window to maximize recovery from the weathered ore. Because the stockpile has been sitting for an extended period, the mineralogy may have shifted slightly due to oxidation, requiring more precise chemical reagent management than during standard “run-of-mine” operations.

Conclusion: A Measured Step Forward
The authorization to remove and process 70,000 tonnes of copper from Cobre Panamá is a pragmatic compromise by the Panamanian government. It addresses immediate environmental concerns and provides a financial bridge for the site’s care and maintenance, all while deferring the politically sensitive decision of a full mine restart until later this year.
As the industry looks toward June, the focus remains on whether Panama can find a regulatory framework that balances its economic ambitions with the environmental and legal standards demanded by its citizens. For now, the “breakout” of the stockpile represents a localized stabilization in what has been a tumultuous period for one of the world’s most significant copper assets.
For more updates on global mining operations and market analysis, visit the Skillings Mining Magazine section.