By Charles Pitts
VANCOUVER, British Columbia : NOVAGOLD Resources Inc. (TSX, NYSE American: NG) reported a net loss of $25.5 million, or $0.06 per share, for the second quarter ended May 31, 2026. The results, released Thursday, reflect the company’s intensified focus on the Bankable Feasibility Study (BFS) for its flagship Donlin Gold project in Alaska, which is positioned to become one of the largest gold-producing assets in the United States.
The second-quarter loss is a widening from the $14.8 million loss reported in the same period in 2025, driven primarily by a more than three-fold increase in the 2026 work program budget. Since restructuring its ownership of Donlin Gold LLC in mid-2025, NOVAGOLD now holds a 60% interest in the project, with the remaining 40% held by Donlin Gold Holdings, an affiliate of Paulson & Co. Inc.
Financial Performance Snapshot
The increased expenditure in Q2 2026 aligns with the previously approved $131.4 million annual budget (100% basis) for the Donlin Gold project. This capital is being deployed to transition the project from technical optimization and permitting toward a construction-ready state.
| Financial Metric (USD) | Q2 2026 | Q2 2025 | Variance (%) |
|---|---|---|---|
| Net Loss | $25.5 Million | $14.8 Million | +72.3% |
| Loss Per Share | $0.06 | $0.04 | +50.0% |
| Cash & Term Deposits | $112.4 Million | $126.1 Million | -10.8% |
| Project Spending (100% basis) | $38.2 Million | $12.5 Million | +205.6% |
“Our financial results for the second quarter are a direct reflection of the momentum we have built at Donlin Gold,” said Greg Lang, President and CEO of NOVAGOLD. “Following the successful selection of our prime engineering partners earlier this year, we are now fully engaged in the Bankable Feasibility Study. This is the most comprehensive technical and financial evaluation in the project’s history, aimed at de-risking the asset and preparing for a formal construction decision.”
Advancing the Donlin Gold Bankable Feasibility Study
The Donlin Gold project, located in the Yukon-Kuskokwim region of southwest Alaska, is one of the world’s largest and highest-grade undeveloped gold deposits. With approximately 39 million ounces of gold in measured and indicated mineral resources at an average grade of 2.24 g/t, the project represents a significant strategic asset in the global gold mining landscape.
In Q1 2026, NOVAGOLD and its partner selected a consortium of global engineering firms to lead the BFS and specialized infrastructure design. The partnership includes Fluor Corporation, WSP, Worley, and Hatch. These firms are tasked with finalizing the designs for the mine’s primary infrastructure, including the power plant, a 315-mile natural gas pipeline, and the high-pressure oxidation (POX) circuit required to process the project’s refractory ore.

The 2026 work program is the most ambitious in the project’s history. Key activities during the quarter included:
- Geotechnical and Hydrological Drilling: Advancing site-specific data collection for the Alaska Dam Safety Certification applications.
- Metallurgical Optimization: Building on the 2024–2025 pilot plant results to refine the flowsheet and maximize gold recovery.
- Regional Exploration: Targeted drilling along the 8-kilometer gold-bearing trend to test for resource extensions beyond the current 27-year mine life plan.
Strategic Ownership and Governance
The project’s progress in 2026 is largely defined by the ownership transition that occurred on June 3, 2025. NOVAGOLD and Paulson’s Donlin Gold Holdings acquired Barrick Gold’s 50% interest in a $1 billion transaction, resulting in the current 60/40 partnership. This move consolidated control among long-term stakeholders committed to the project’s development in Alaska.
The shift in ownership has led to an accelerated development timeline. Under the leadership of Project Director Frank Arcese, the Donlin Gold LLC team has ramped up site activity, with the 2025 field season seeing a significant increase in local employment. Approximately 53% of the project’s workforce in 2025 were Calista and The Kuskokwim Corporation (TKC) shareholders, a trend NOVAGOLD expects to continue throughout the BFS and eventual construction phases.
Liquidity and Capital Requirements
As of May 31, 2026, NOVAGOLD maintained a treasury of $112.4 million in cash and term deposits. While the company remains well-funded for the immediate BFS requirements, management noted that future project development will require significant capital raises. The total initial capital cost for Donlin Gold was previously estimated at approximately $7.4 billion (100% basis), though this figure is expected to be updated as part of the BFS results.
NOVAGOLD’s strategy remains focused on maintaining a strong balance sheet while advancing the project toward a “final investment decision” (FID). The company has indicated it will evaluate various financing options, including potential strategic partnerships or capital markets activity, as the BFS nears completion in 2027.

Market Outlook: The Race for Domestic Supply
The advancement of Donlin Gold comes at a time of heightened interest in domestic mineral security. As one of the top mining projects in the USA, Donlin Gold is frequently cited by policymakers as a critical component of the American resource strategy.
The project benefits from being located on private Alaska Native corporation land, designated for mining under the Alaska Native Claims Settlement Act (ANCSA). This unique land status, combined with the project’s federal permits being in good standing, provides a degree of regulatory stability compared to projects on federal public lands.
However, the path to production is not without hurdles. The project continues to navigate the Alaska Dam Safety Certification process and manages ongoing legal appeals regarding certain state permits. NOVAGOLD management remains confident in the robustness of the environmental impact statements (EIS) and the technical merit of the dam designs.
Operational Logistics and Control
Managing a project of Donlin Gold’s scale in a remote Arctic environment requires sophisticated logistics and real-time oversight. The company has invested heavily in remote monitoring and data integration to coordinate the BFS activities between the Vancouver headquarters, the Anchorage office, and the Crooked Creek site.

The use of advanced telemetry and autonomous-ready systems is being integrated into the BFS mine plan. By leveraging modern fleet management technology, NOVAGOLD aims to offset the high operational costs associated with the project’s remote location.
Conclusion
NOVAGOLD’s Q2 2026 results confirm the company’s transition from a “permitting and holding” phase into an intensive “engineering and design” phase. While the net loss reflects the heavy spending required to bring a Tier 1 asset to feasibility, the project’s scale and grade continue to distinguish it within the global gold sector.
Investors and industry analysts are closely watching for the mid-study updates from Fluor and Hatch, which will provide the first significant cost and production refinements since the ownership change in 2025. With gold prices remaining buoyant in 2026, the economic incentive to bring Donlin Gold online has never been higher.
Featured Lead Social Media Snippet
LinkedIn/X:
NOVAGOLD (NG) reported Q2 2026 results today, highlighting a $25.5M net loss as it triples spending on the Donlin Gold Bankable Feasibility Study in Alaska. With partners like Fluor, Hatch, and Worley on board, the project is moving closer to becoming the largest gold mine in the US.
Key Takeaways:
? 60% NOVAGOLD / 40% Paulson ownership structure
? $131M 2026 work program in full swing
? Focus on Dam Safety and POX infrastructure design
Read the full analysis on Skillings Mining Intelligence: [Link]
#GoldMining #Alaska #Novagold #MiningNews #DonlinGold #ESG #MiningFinance
Market Snapshot: US Gold Development Projects (June 2026)
| Project | Owner | State | Resource (M&I) | Status |
|---|---|---|---|---|
| Donlin Gold | NOVAGOLD/Paulson | Alaska | 39.0 Moz | BFS Underway |
| Stibnite Gold | Perpetua Resources | Idaho | 6.0 Moz | Permitting/Early Works |
| Goldlund | Treasury Metals | Ontario (CA) | 2.1 Moz | PEA/DFS |
| Back River | B2Gold | Nunavut (CA) | 6.3 Moz | Construction |