TORONTO : Ontario has designated Kinross Gold Corp.'s Great Bear gold project as the first mining development to receive accelerated permitting under the province's "One Project One Process" framework, a move aimed at cutting approval timelines from more than a decade to approximately two years.
The C$1.4 billion project, located 23 kilometers southeast of Red Lake in northern Ontario, becomes the inaugural recipient of the fast-track designation announced by the provincial government Tuesday. The framework coordinates approvals across ministerial, Indigenous, and federal levels to streamline what has historically been a fragmented permitting process.
Great Bear represents a high-grade combined open-pit and underground operation that will include two open pits and an on-site processing mill. According to Kinross's 2024 preliminary economic assessment, the project is expected to produce over 500,000 ounces of gold annually at an all-in sustaining cost of approximately $800 per ounce during its first eight years of operation.

Resource Base and Production Timeline
The mineral resource at Great Bear consists of 30.3 million measured and indicated tonnes grading 2.81 grams gold per tonne, containing 2.7 million ounces of gold. An additional 25.5 million inferred tonnes at 4.74 grams gold per tonne hold 3.9 million ounces.
The project has an initial planned mine life of approximately 12 years, though federal environmental assessment documentation indicates the overall operation could extend to about 20 years depending on exploration success and gold prices.
Kinross is currently advancing detailed engineering and procurement activities, with manufacturing of long-lead equipment items anticipated to commence in 2026. The company has not announced a formal construction decision timeline but stated the accelerated permitting framework significantly de-risks the development schedule.
Infrastructure Coordination
Ontario tied the Great Bear designation to broader regional infrastructure development, specifically the planned Red Lake Transmission Line that would supply electricity to multiple mining operations in the area. Provincial forecasts indicate electricity demand in the Red Lake region is expected to grow by up to 250 percent by 2050, driven primarily by mining sector expansion.
The transmission line project remains in early planning stages, with detailed routing and Indigenous consultation processes still underway. The coordination between mine permitting and infrastructure development represents a shift in Ontario's approach to managing large-scale resource projects.

Permitting Framework Details
The "One Project One Process" framework establishes a single coordinated review process led by a designated provincial ministry. For Great Bear, the Ministry of Mines will serve as the primary coordinator, working directly with the federal Impact Assessment Agency, the Ministry of the Environment, Conservation and Parks, and multiple Indigenous communities with traditional territories in the region.
The two-year target timeline represents a substantial reduction from typical Ontario mining permit approvals, which have averaged 10 to 15 years over the past decade when accounting for environmental assessments, Indigenous consultation, and various ministerial approvals.
Provincial officials stated the framework does not eliminate any consultation requirements or environmental review standards but instead runs previously sequential processes in parallel where feasible. Indigenous consultation remains a mandatory component throughout the process, with formal agreements required before project approval.
Economic and Employment Projections
Kinross estimates Great Bear will create approximately 450 direct jobs during construction and 500 permanent positions during operations. The company projects annual payroll of approximately C$50 million at full production, with additional indirect economic activity in Red Lake and surrounding communities.
The mine's all-in sustaining cost target of $800 per ounce positions it in the lower half of the global cost curve for gold production. With gold prices trading above $2,800 per ounce in February 2026, the project economics remain robust even under conservative price scenarios.
Ontario's mining sector currently employs approximately 75,000 people directly and generates roughly C$10 billion in annual mineral production. Provincial officials stated the Great Bear fast-track designation is part of a broader strategy to maintain Ontario's competitiveness as mining jurisdictions globally compete for capital investment.

Industry and Investment Context
The Great Bear designation comes as gold mining companies face increasing competition for capital amid uncertainty around long-term gold price forecasts and shifting investor priorities toward battery metals and critical minerals.
Canada's mining permitting timelines have drawn criticism from industry groups, with the Mining Association of Canada stating in a 2025 report that regulatory uncertainty and extended approval processes have deterred an estimated C$15 billion in potential mining investment over the past five years.
The Fraser Institute's 2025 Annual Survey of Mining Companies ranked Ontario 23rd globally for policy attractiveness, down from 12th in 2020. The province cited permitting delays and policy uncertainty as primary factors in the decline.
Ontario's government stated the "One Project One Process" framework could be extended to additional mining projects if the Great Bear pilot proves successful. Provincial officials did not specify criteria for selecting future projects but indicated preference for developments with significant employment potential and alignment with regional infrastructure planning.
Environmental and Community Considerations
Great Bear's environmental assessment process will evaluate potential impacts on water quality, wildlife habitat, and traditional land use by Indigenous communities. The project site is located within the traditional territories of multiple First Nations, including Wabauskang First Nation and Lac Seul First Nation.
Kinross stated it has signed memorandums of understanding with several Indigenous communities and is negotiating impact benefit agreements that would provide employment opportunities, business contracts, and revenue sharing. The company did not disclose financial terms of the agreements.
Federal environmental assessment processes remain mandatory for projects of Great Bear's scale, requiring coordination between provincial and federal agencies. The integrated review process is designed to minimize duplication while maintaining environmental oversight standards.
Market and Strategic Implications
Great Bear's advancement occurs as gold mining companies prioritize high-grade, low-cost deposits to maintain margins amid rising input costs and labor expenses. The project's grade of 2.81 grams per tonne in measured and indicated resources exceeds the global average for open-pit gold deposits, which typically ranges between 1.0 and 1.5 grams per tonne.
Kinross operates six mines globally, with recent strategic focus on consolidating operations in favorable jurisdictions. The company sold its Russian assets in 2022 and has increased exploration spending in the Americas, where regulatory frameworks are considered more stable than in certain African and Asian jurisdictions.
The Red Lake district has produced over 30 million ounces of gold since operations began in the 1930s, with historical grades among the highest globally. Recent discoveries, including Great Bear, have renewed interest in the region after a period of declining production in the 2010s.
Ontario's mining sector faces competition for investment capital from jurisdictions including Nevada, Western Australia, and Quebec, which have implemented various incentive programs and permitting reforms to attract development capital.
The Great Bear fast-track designation will be monitored closely by other provinces and the federal government as Canadian jurisdictions evaluate strategies to accelerate resource development while maintaining environmental and social standards.